Fermilab, Batavia, Illinois
National Accelerator Laboratory 15 kV Cable Installation
Installation of 41,000 LF of government-furnished 750 MCM 15 kV shielded cable with 84 underground splices and terminations.
Project Details
- Owner
- U.S. Department of Energy
- Role
- Contractor
- Contract Value
- $317,000.00
- Status
- In progress
Project Overview
Overstreet Electric is being awarded the contract to install government-furnished 15 kV cable at the National Accelerator Laboratory, subject to a 60-day performance period.
Scope Highlights
- 41,000 LF of government-furnished #750 MCM 15 kV shielded cable
- (84) 15 kV underground splices and terminations
- Over 30,000 LF of coaxial cable and HELIAX cables
- Fireproofing of new cable and splices in more than 25 manholes
Related Projects
More work like this
Fort Sill, Oklahoma
Feeder 5 Electrical Upgrades
Design-build modification of the existing 13.2 kV overhead distribution system on Fort Sill, improving the reliability and safety of the installation's electrical network.
Kennedy Space Center, Florida
Replace Transformer SS-849 & Panel CP
Fast-track replacement of a unit substation with stainless-steel equipment, executed within a single 8-hour scheduled outage.
Wright-Patterson AFB, Ohio
Electrical Upgrades, Area B
Replaced a loop-fed 6.9 kV distribution system with a new 15 kV system and installed a new 100 MVA power transformer — across 60+ buildings.