Replace Transformer SS-849 & Panel CP
Fast-track replacement of a unit substation with stainless-steel equipment, executed within a single 8-hour scheduled outage.
Project Details
- Owner
- NASA
- Role
- Contractor
- Contract Value
- $408,000.00
- Status
- In progress
Project Overview
Overstreet is removing and replacing an existing unit substation at Kennedy Space Center. The cut-over is performed as a single 8-hour scheduled power outage, followed by furnishing, installing and maintaining a 200 kW generator and fuel tank on a 24-hour basis until project completion.
The scheduled performance period is 60 days, subject to final acceptance, on a fast-track construction schedule.
Scope Highlights
- New 300 kVA pad-mounted stainless-steel transformer
- New 15 kV stainless-steel sectionalizing cabinet
- New 800 A NEMA 4X stainless-steel panelboard and custom NEMA 4X stainless splice box
- New Camlock generator receptacle
- New 15 kV feeders and duct banks
- New digital demand & revenue meter, CTs, CPT, control wiring, communication-protocol programming and demand settings
Outcomes
- Entire cut-over performed within a single 8-hour scheduled outage
- 60-day scheduled performance period
More work like this
Feeder 5 Electrical Upgrades
Design-build modification of the existing 13.2 kV overhead distribution system on Fort Sill, improving the reliability and safety of the installation's electrical network.
National Accelerator Laboratory 15 kV Cable Installation
Installation of 41,000 LF of government-furnished 750 MCM 15 kV shielded cable with 84 underground splices and terminations.
Electrical Upgrades, Area B
Replaced a loop-fed 6.9 kV distribution system with a new 15 kV system and installed a new 100 MVA power transformer — across 60+ buildings.