13.8 kV Substation Upgrade, Jim Woodruff Powerhouse

Substation modernization at a hydroelectric powerhouse — SF6 switches, 115 kV circuit switchers, armor-clad turbine feeders and a new underground utility tunnel.

Project Details

Owner
U.S. Army Corps of Engineers, Mobile District
Role
Prime Contractor
Contract Value
$2,701,000.00
Status
Completed · awarded FY 1998
Job #
9804

Project Overview

Overstreet provided all labor, materials and equipment to modernize the 13.8 kV substation at the Jim Woodruff Powerhouse.

Scope Highlights

  • Replaced existing oil switches with new SF6 switches; replaced disconnect switches
  • 115 kV circuit switchers, bussing and ground grid
  • New 15 kV armor-clad feeders to the existing turbines
  • New concrete foundations and fire walls for power transformers; new ventilation building
  • New 100-ft-long, 12-ft-wide × 10-ft-high poured-in-place concrete utility tunnel, 20 ft deep, with sheet piling
  • Modified the control switchboard and replaced all control and relay wiring
  • Overcurrent relays, cable tray and vacuum circuit breakers for existing switchgear

Legacy project performed by the predecessor firm, Overstreet Electric Co., Inc.